THE PORT OF HUELVA BEGINS DREDGING OPERATIONS

Huelva Port launches the most important work in order to sustain the future of all its activities.
The project contemplates an increase in the draft of the navigation channel to 14.5 meters; a new maneuvering area in front of the South Pier; an increase in draft in the mooring pit and the access area at the South Pier and in the North Extension of the South Pier.
This is an infrastructure demanded by practically all the operators that work in the Huelva docks that have been asking for deeper funds for years to be able to operate larger ships.
The planned budget for the implementation of technical assistance is divided into two amounts of 145,200 euros for this year and 278,300 euros for next year and could be completed by 2022 , just when the Port plans to enter into service all the infrastructure of the South Pier.

Table of Contents
Related posts

From 1 May 2025, ships operating in the entire Mediterranean Sea will be required to burn fuel oil with a

Naturgy and the Norwegian Equinor have gone a step further in their alliance in offshore wind power with the signing

Depósitos Portuarios, SA (Deposa) terminal has completed the construction of six new agri-food and agro-energy liquid bulk storage tanks in